Engineering Reference · Lead Times

Lead times and the China production calendar

"20 days" is the most quoted and least reliable number in cosmetic packaging. The honest figures, factory gate and before freight: stock components 7–25 days; screen print or hot-stamp +5–7; spray coating 30–40; glass 30–60; tubes and pouches 15–20; private tooling 45–60 days for the mould and 90–120 days for the full programme. Multiply any schedule by 1.3 for buffer, add 15 days if it crosses Chinese New Year (6 February 2027), and then add freight — typically 18–25 days by sea to the US West Coast, 30–35 to Northern Europe, 20–25 to Australia, 3–7 days by air. Below is where each of those days goes, and the calendar that moves them.

Figures reflect common industry thresholds and partner-factory practice, August 2026; product-specific values are agreed in your specification. Vella is a sourcing partner working with vetted partner factories operating to ISO 22716 / GMP; freight figures are carrier-dependent planning values, not guarantees.

Ten Nodes

Where lead time actually goes.

A factory's "production time" is one of ten nodes. The other nine are where orders slip, and most of them are invisible in a one-line quote. Here is the full chain, with typical durations and the usual failure point at each step:

#NodeWhat happensTypical durationWhere it slips
1Order processingReview and entry: quality standard, delivery date, quantity, price and currency, payment terms, packing, transport, destination, contact1–2 daysMissing or ambiguous spec; PO that does not match the quote; unsigned golden sample
2Production planningSlot the order against capacity, material, quality and process readiness; PMC issues material and production plans1–3 daysFactory already at >85% load; planning done by the production manager rather than an independent PMC
3Raw-material purchaseResin (PET, PP, ABS, PETG), glass, aluminium, pumps, plus decoration materials (inks, foils, coatings)3–15 days (colour-matched masterbatch and speciality resins at the long end)Custom colour masterbatch; imported resin grades; pump sub-supplier MOQ
4Outsourced processesSpray coating, plating, printing, hot-stamping, anodising at specialist sub-contractors5–20 days depending on process and sub-contractor queueSub-contractor peak-season queue; environmental inspection closures; transport between plants
5Incoming inspection (IQC) and warehousingMaterials and bought-in components checked against spec before release to production1–2 daysRejected resin lot or pump batch — restarts node 3
6Production preparationMould loading, machine set-up, work instructions, first-article approval, inspection tooling ready1–3 daysMould in maintenance; colour change on the line; first article fails against golden sample
7ProductionMoulding / blowing / forming, then assembly3–15 days by quantity and cavitationMachine breakdown; yield below plan; power restriction days
8Final inspection and warehousing (FQC / OQC)Finished goods against golden sample, AQL sampling, packing verification1–3 daysColour drift beyond agreed ΔE; sorting required; pre-shipment inspection booking
9LogisticsExport packing, booking, transport to port or airport, customs, main leg, destination clearanceSea typically 18–35 days port to port; air typically 3–7 daysBlank sailings; peak-season space; documentation errors
10BufferReserved time for weather, production anomalies, holidays and the unknownSchedule × 1.3; +15 days across Chinese New YearA quote without a buffer is a quote that assumes nothing goes wrong

The arithmetic: processing + planning + materials + outsourced processes + IQC + preparation + production + FQC/OQC + logistics + buffer. A stock bottle that "takes 10 days to mould" is a 21–27-day factory-gate order once the chain is added up, and a 45–60-day door-to-door order once it is on a ship. That is not slowness — it is the real shape of the work. A quote that ignores it is optimistic, not fast.

Standard Cycles

Standard cycles by category.

Factory-gate figures for partner factories under normal load, after order review and with an approved golden sample in hand. Decoration adds to the base; calendar effects add to everything.

CategoryScopeStandard cycle (factory gate)Notes
Stock (public-mould) components, undecoratedPET / PETG / PP / HDPE bottles, jars, caps, standard pumps in stock colours7–25 days7–10 days if in stock and only needs packing; 15–25 if a run is required
Screen printing or hot-stampingAdded to any of the above+5–7 daysPlate or foil block making 2–3 days; ≤2 decoration processes per part is the practical limit
Spray-coated bottles and capsColour or matte coating, usually outsourced30–40 daysColour approval on a sprayed sample first; coating adhesion tested with 3M 810 cross-hatch
Glass bottles and jarsStock moulds, flint or amber; longer for custom colour, frosting, coating and printing30–60 daysGlass furnaces run to campaign schedules; a colour change on the line is planned weeks ahead
Plastic tubesMono-layer, 5-layer EVOH and ABL, printed15–20 daysMOQ typically 5,000–10,000; ±10% over/under delivery is industry practice; plate cost approx. USD 28–42 (RMB 200–300 at 7.2)
Aluminium and laminate pouches / sachetsPrinted foil laminate, stand-up or flat15–20 daysCylinder or plate making adds 5–7 days on a new artwork
Airless bottles, stockStock tooling, standard colours20–30 daysPiston and pump sub-assemblies come from separate lines; compatibility test with your bulk in parallel
Aluminium componentsLipstick shells, overcaps, anodised parts25–40 daysAnodising colour matching; a second anodising batch rarely matches the first without a control sample
Private tooling — mould onlyInjection or blow mould, first shots, mould trials45–60 daysMould precision ≤0.05 mm, polish Ra ≤0.2 μm; first-article full-dimension report to ±0.1 mm; 500-piece trial run at ≥95% yield
Private tooling — full programmeBrief → 3D → mould → first shots → structure review → compatibility test → pilot run → mass production90–120 daysThe 48°C / 30-day compatibility test runs inside this window, starting on the first approved shot

Buffer factor ×1.3: the quoted cycle is the plan; the buffered cycle is the promise. We commit dates on the buffered figure and report progress against the plan, so an order that runs to plan arrives early, and an order that hits a normal delay still arrives on the date you were given. Across Chinese New Year the buffer is a flat +15 days on top.

The Calendar

The Chinese production calendar.

Every lead time above lives inside a calendar that a Western planning tool does not know about. Seven events matter; the first one matters most.

PeriodWhenWhat happens in the factoryPlanning rule
Chinese New Year (Spring Festival)2027: 6 February; 2028: 26 JanuaryFactories close 2–3 weeks; reduced capacity 1–2 weeks after as workers return; the month before is the busiest of the year+15 days on any order touching the period; confirm pre-holiday shipments by early December; January confirmations are realistically March deliveries
National Day Golden Week1–7 October every yearFull stop for 5–7 days; sub-contractors and freight forwarders also close; port congestion before and after+7–10 days on orders in flight; book vessel space before the third week of September
Peak seasonSeptember–NovemberPre-Black Friday, Singles' Day, Christmas and pre-CNY orders compete for the same machines and decoration linesCapacity typically tight; expect standard cycles at the top of their range; confirm Q4 requirements by July–August
Environmental production restrictionsUnannounced; most frequent in winter heating season (November–March) and around major national eventsSpray-coating, plating and glass furnaces are the first to be curtailed; one-to-two-week stoppages at sub-contractors are commonThis is the main reason the buffer exists; decoration-heavy programmes carry the highest exposure
Summer power rationingJuly–August in hot years, provincialRotating 'work 4 stop 3' schedules in some industrial zones+3–7 days on moulding-heavy orders
Other public holidaysQingming (early April), Labour Day (1–5 May), Dragon Boat (June), Mid-Autumn (Sept/Oct)1–5 day stopsMinor individually; cumulative if an order spans several
Freight peakAugust–October and the 4 weeks before CNYBlank sailings, rolled bookings, rate spikesBook 3–4 weeks ahead; budget for space, not just rate

Practical rule for Q1 launches: if you need goods in the US or Europe before the end of March, the factory order must be confirmed — golden sample signed, deposit paid — by the first week of December. Anything later is competing with the busiest month of the Chinese year and then waiting for the holiday to end.

Order Review

Why we do not quote a date before the review.

The four order types that reliably run late are known in advance: the rush order with a client-set date nobody checked against capacity; the order taken before the specification was finished; the order accepted without a review at all; and the order for a product that was not yet mature — where the material buying window gets squeezed, the line waits for parts, and the specification changes mid-run. The prevention is a fixed step, not good intentions.

Order review checks three things before a date is committed: capacity — current and forecast load on the specific moulding machines and decoration lines, including sub-contractors; quality readiness — signed golden sample, drawings, inspection standards, test equipment and incoming-inspection criteria in place; lead time — raw material and pump availability, outsourced process queues, and logistics space. Repeat orders of an approved item go through a short-form review in hours; new formats, new decoration or new factories get a full review, which takes one to two working days. The date you receive after that review is the one we are prepared to be measured on.

Tracking

Three alert levels and one number.

Progress is followed on the floor, not by email: roughly 80% of order follow-up time is spent at the material store, the moulding hall, the decoration sub-contractor and the inspection room, because that is where the true status is. When an order drifts, the response is pre-agreed:

LevelTriggerActionCommunication
Yellow3 days behind plan at any node, or a sub-contractor missing a dateWritten recovery plan from the factory within 24 hours; daily follow-up until back on planInternal; client informed if the shipping date is at risk
Orange7 days behind plan, or a repeated yellow on the same orderDaily reporting; overtime, second shift or parallel capacity; part-shipment options costedClient informed with revised date and options
Red10 days behind plan, or any confirmed risk to the ship dateAlternative factory or split production activated from the pre-qualified pool (target: switchable within 72 hours for stock formats); air-freight top-up costedClient decision meeting within 24 hours; nothing is decided for you

OTD — on-time delivery — is the one number that summarises all of this. It is measured against the reviewed, confirmed date, per order line, per partner factory. Below 90% three orders in a row and a factory loses allocation to another in the pool; consistently above 95% and it gets the next private-tooling programme. If you ask a supplier for its OTD figure and get an adjective back, you have your answer.

Freight

Shipping time from China, for planning.

Port-to-port sea figures and door-to-door air figures, as carriers have typically been running. Add 5–10 days at each end for customs, port handling and inland transport, and add the pre-shipment inspection window before departure.

RouteSea freight, port to portAir freight, door to door
China (South China ports) → US West CoastTypically 18–25 daysTypically 3–7 days
China → US East CoastTypically 30–40 daysTypically 3–7 days
China → Northern Europe (Rotterdam, Hamburg, Felixstowe)Typically 30–35 daysTypically 3–7 days
China → MediterraneanTypically 25–32 daysTypically 3–7 days
China → Australia (East Coast)Typically 20–25 daysTypically 3–6 days
China → UAE / GulfTypically 18–25 daysTypically 3–5 days
China → Southeast AsiaTypically 5–12 daysTypically 2–4 days
Worked Examples

Why "20 days" is not a delivery date.

Take the most common brief we receive — a stock bottle, a stock pump and one print — and walk it through the chain. The number a factory quotes and the number you can plan a launch around are different things, and the gap is not dishonesty; it is the nine nodes that a factory-gate quote does not include.

OrderQuoted cycleBufferedRealistic delivery
Stock PETG bottle + lotion pump, screen-printed, 10,000 pcsStock 15 + print 6 = 21 days21 × 1.3 = 27 days+ sea to US West Coast 18–25 + clearance 5–10 = 50–62 days door to door
Same order confirmed 10 January 202721 days27 + 15 (CNY) = 42 days factory gateMid-March ex-factory; early-to-mid April in the US
Sprayed glass jar, custom colour, 5,000 pcsGlass 45 + spray 35 (partly parallel) ≈ 60 days60 × 1.3 = 78 days+ sea to Europe 30–35 + clearance = 115–125 days
Private-mould airless bottle, new toolingMould 50 + programme total 90–120 daysAlready buffered inside the 90–120 window; add CNY if crossedPlan launch 5–6 months from brief; run the 48°C / 30-day compatibility test from the first approved shot

A "20-day" promise fails one of three ways: it is the production node alone (nodes 1–6 and 8–10 missing); it was given before an order review (capacity and materials unchecked); or it ignores the calendar (a January promise that meets February). None of those is fast. Fast is a reviewed 27-day factory-gate commitment that ships on day 25.

If you genuinely have 20 days: restrict yourself to undecorated stock components already in a partner factory's warehouse, accept the factory's stock colours, ship by air, and confirm the same day the samples are approved. It is achievable for a pilot batch; it is not a way to run a range.

Questions

Frequently asked

How long does cosmetic packaging take to produce in China?
It depends on the route, and the honest numbers are these: stock components 7–25 days; add 5–7 days for screen printing or hot-stamping; spray-coated bottles 30–40 days; glass 30–60 days (longer for custom colour or decoration); tubes and aluminium pouches 15–20 days; private tooling 45–60 days for the mould and 90–120 days for the whole programme from brief to first delivery. All of these are factory-gate figures before freight and before any calendar effect.
Why should I not trust a 20-day lead time quote?
Because a factory-gate figure only covers the production node. A real lead time has ten nodes: order processing, planning, raw-material purchase, outsourced processes such as decoration, incoming inspection, production preparation, production, final inspection and warehousing, logistics, and a buffer for the unexpected. A quote of 20 days that has not been through an order review of materials, capacity and QC readiness is a hope, not a commitment. Our rule: multiply the quoted schedule by 1.3, add 15 days if it crosses Chinese New Year, and only then commit a date.
When is Chinese New Year 2027 and how does it affect packaging lead times?
Chinese New Year falls on 6 February 2027; the official holiday is about a week, but factories typically stop for 2–3 weeks and run at reduced capacity for another 1–2 weeks as workers return. Plan for +15 days on any order that touches the period, and expect capacity to be tight for the whole month before it as factories clear pre-holiday backlogs. Orders that must ship before the holiday should be confirmed by early December; anything confirmed in January is realistically a March delivery.
What is an order review and why does it come before a delivery date?
An order review checks three things before anyone promises a date: capacity (current and forecast load on the specific machines and decoration lines), quality readiness (approved golden sample, drawings, test equipment, incoming-inspection standards in place) and lead time (raw material availability, outsourced processes, logistics). Orders that skip it are the ones that slip: rush orders with a client-set date nobody checked, orders taken before the specification was finished, and orders where the product was not yet mature. We do not commit a date before the review is complete — that takes a day or two, and it is why the date holds.
How long does shipping take from China for cosmetic packaging?
Port to port, sea freight from South China is typically 18–25 days to the US West Coast, 30–35 days to Northern Europe, 20–25 days to Australia, and roughly 30–40 days to the US East Coast. Air freight is typically 3–7 days door to door. Add 5–10 days at each end for customs clearance, port congestion and inland haulage, and add the pre-shipment inspection window before departure. These are planning figures, not guarantees; carriers, routings and peak-season blank sailings move them.
What is OTD and what on-time delivery rate should I expect?
OTD is on-time delivery: the share of order lines delivered on or before the committed date, measured against the reviewed and confirmed date, not the date first requested. We track it per partner factory and use a three-level alert system: yellow at 3 days behind plan (written recovery plan within 24 hours), orange at 7 days (daily reporting, overtime or parallel capacity), red at 10 days or any risk to the ship date (client informed, alternative factory or split shipment activated). Factories that fall below 90% OTD three times in a row lose allocation. A supplier that cannot tell you its OTD figure is not measuring it.
Ready to source?

Get a date that holds.

Tell us the format, quantity and the date you actually need it. Your quote comes back with the ten-node breakdown, the buffered commitment and the calendar risks marked.

Reply within 24h · NDA on request · Your details stay confidential

Keep Reading

Related reading.