Engineering Reference · Moulds

Mould cost and mould ownership, with the numbers

A custom cosmetic packaging mould is quoted from eight items: material 15-30%, machining and toolmaker's margin 30-50%, design 10-15%, trial moulding ≤3-5%, freight ~3%, overhead up to 20%. A plastic injection tool prices at about 6 × its material cost; a worked mid-size example comes to RMB 76,500 (approx. USD 10,600). It is paid 30/40/30, rated for 800,000 cycles, and — if the contract says so — it belongs to you, transferable to another factory at any time. Below: the tables, the glass-mould fees, and the six clauses that go with a private mould.

Figures reflect common industry thresholds and partner-factory practice, August 2026; product-specific values are agreed in your specification.

Cost Structure

What a mould quote is made of.

Toolmakers in the cosmetics packaging belts (Guangzhou, Shantou, Yuyao, Shangyu) build a quote from the same eight items. The proportions below are the working ranges we see; the sum is what you should be able to reconcile line by line before you pay a deposit.

Cost itemTypical share of totalWhat it covers
Material15-30%Mould base, cavity and core steel (P20, 718, S136, 2738 by finish and life), standard parts
Machining + toolmaker's margin30-50%CNC, EDM, wire-cut, grinding, polishing, fitting, assembly; the toolmaker's profit sits here
Design10-15% (often 6-10%)3D data, DFM, mould-flow analysis, assembly and part drawings, process card
Trial moulding≤3% medium/large, ≤5% small precisionUsually 3 trials included; extra trials billed at around RMB 500 (approx. USD 70) each
Packing & freight~3%Crating, delivery of the tool and sample shipments; often charged to the buyer
Management overheadup to 20%Project management, QA, documentation, tool-shop overhead
Risk allowance~10%Engineering changes, rework, steel price movement
Labour, outsourcing, consumables5-15% combinedHand finishing, texturing or heat-treatment sub-contracted, cutting tools

The material-coefficient cross-check. If you do not want to audit eight lines, use the rule of thumb toolmakers use on each other: a plastic injection mould prices at about 6 × its material cost (forging dies likewise; die-casting moulds nearer 10 ×). A quote whose material line is RMB 25,000 and whose total is RMB 150,000 is either an unusually complex tool or an unusually optimistic margin, and either way deserves a question.

Worked Example

A plan-cost sheet for a mid-size single-component tool.

This is the shape of a toolmaker's internal cost sheet for a typical cosmetic component mould (a cap or a jar body in the 50-100 g range). The percentages are the toolmaker's own targets; the total is about RMB 76,500, approximately USD 10,600 at 7.2.

LineRMBShareUSD (approx.)
Design8,0005-9%1,110
Material (base, steel, standard parts)25,00020-33%3,470
Machining10,00010-12%1,390
Labour (fitting, polishing)10,0008-11%1,390
Modification allowance5,0005%695
Outsourced processes2,5003%350
Trial moulding (3 trials; extra at RMB 500 each)1,5001.5-3%210
Freight and sample shipping (buyer's account)3,0003%415
Cutting tools and consumables1,5001.5%210
Management overhead10,0005-10%1,390
Total≈76,500100%≈10,600

Toolmakers normally add 10-30% to the plan cost for the first quote. The number that matters to you is the re-review line: a negotiated price more than 10% below the toolmaker's own estimate sends the job back for re-costing, and in practice that re-costing comes out of steel grade, hardening or the number of trial shots. Bargain on scope and payment terms, not below that line.

Cavities & Life

Cavity count, unit cost and how long the tool lasts.

A mould's price is paid once; its cavity count is paid on every shot. More cavities raise the tool price and lower the cycle cost per piece, so the right count depends on annual volume and tolerance, not on the lowest quote.

PartTypical cavitiesWhy
Precision parts (grade 3-3a, ~5 g: dispenser internals, valve seats)4-6Tighter tolerances need fewer, better-balanced cavities; often a hot-runner system
Small parts 12-16 g (caps, discs, inner plugs)8-12Volume parts at normal tolerance (grade 4-5)
Medium parts 50-100 g (jar bodies, thick-wall caps)4-8Cooling time and platen size limit the count
Standard-tolerance semi-crystalline parts (PP, PE closures)16-20Where volume justifies it; grade 7-9 tolerance can take up to 50% more cavities than grade 4-5

Rated life is about 800,000 cycles for a hardened steel injection mould. Use and maintenance account for 15-20% of the variation in real life; with first-line daily care (clean, lubricate, inspect) and second-line fitter maintenance (polish and weld-repair forming faces, stone the guides, replace springs only with matching colour, outer diameter and length, use standard punches and bushes) the same tool runs 2-3 times that. Neglected tools reach one-fifth to one-third of rated life. Acceptance is checked against hard numbers, not a hand-shake: forming steel ≥50 HRC (surface-hardened ≥600 HV), cooling circuit leak-free at 0.5 MPa, temperature spread across each water line <3°C, flatness on small parts <0.3 mm, weld-line at round through-holes ≤5 mm, mating-surface mismatch <0.1 mm.

Trial moulding is where irreversible decisions get made. A proper T1 runs the new settings for at least 30 minutes before a full set of samples is shot, with hold pressure at 90-95% and a screw cushion of about 10%. Problems are solved by changing process conditions first; the mould is only cut when process cannot solve it, because once steel is removed it cannot be put back. Every mould change must be notified to and approved by the buyer before it is made — a rule we write into the agreement.

Glass

Glass moulds cost less; the MOQ is the real gate.

Glass mould typeRMB per setUSD (approx.)Notes
Hand-blown (manual) mould~2,500~350Low-volume, artisanal shapes; slower and less consistent
Automatic-line mould, single cavity~4,000~555Standard for dropper, serum and perfume bottles
Automatic-line set, 4-8 cavities16,000-32,0002,200-4,450Depends on the glassworks; needed for economic runs

Custom glass carries a 30,000-200,000 piece minimum and a 30-60 day lead time; decoration adds roughly RMB 0.5-1.1 per piece for spray coating, RMB 0.1 per colour for screen print and about RMB 0.4 per design for hot-stamping. If your first order is under the glassworks' minimum, a stock bottle from our glass bottle range with private decoration is usually the better use of the mould budget. See real MOQs by route.

Ownership & Terms

Who owns the mould, and the six clauses that go with it.

A private mould belongs to the brand that paid for it. The factory holds it in custody and may use it only for that brand's orders. The agreement should say so in one paragraph: ownership with the brand; custody, maintenance and insurance duty with the factory; no use for any third party; and the brand's right to transfer the tool to another factory at any time on written notice, once any outstanding balance is settled. At the end of a programme the usual options are buy-back at an agreed depreciated value, scrapping, or transfer — and the agreement should fix the method and the pricing basis before the first shot, not at the exit. Our sourcing-agent service writes this into every private-mould project.

ClauseWorking thresholdWhat it prevents
Capacity reservationReserved capacity ≥ 120% of forecast order volumePeak-season stock-outs when the factory takes a bigger customer
Price adjustmentRenegotiation triggered when resin/raw-material price moves ±10%Absorbing a 30% PET spike with no mechanism, or paying 2025 prices in a falling market
Mould ownershipBrand owns; factory has use rights for brand orders only; transferable on noticeYour bottle appearing under another label
Anti-counterfeitFactory co-operates on security codes; cost-sharing scheme agreedGrey-market fakes (one programme cut counterfeit share from 15% to 0.3%)
MOQ flexibilitySurplus above 20% of the order can be cancelledDead stock financed by you
Second-source switchIf primary fails to supply for ≥5 days, the qualified second source starts automaticallyLegal delays while your line is down

One honest boundary: we are a sourcing partner working with vetted partner factories, not the toolmaker. That is exactly why the ownership clause matters to us — it is the document that lets us move your tool if a factory stops performing. Partner factories operate to ISO 22716 / GMP; the mould agreement sits alongside the QC standards applied to every order.

Questions

Frequently asked

How is a cosmetic packaging mould quoted?
A mould quote is built from eight items: material (mould base, steel, standard parts) at 15-30% of the total, machining plus the toolmaker's margin at 30-50%, design at 10-15%, trial moulding at no more than 3% for medium and large tools or 5% for small precision tools, packing and freight at about 3%, and management overhead at up to 20%. A quicker cross-check is the material-coefficient method: a plastic injection mould typically prices at about 6 times its material cost. A worked plan-cost example for a mid-size single-component tool comes to roughly RMB 76,500, approximately USD 10,600 at 7.2.
What is the 30/40/30 mould payment structure?
The 30/40/30 structure, which Chinese toolmakers call san-si-san, is 30% deposit on signing, 40% after the design review (DFM and mould-flow sign-off), and 30% within one week of acceptance and hand-over. The alternative 50/50 structure is 50% on signing and 50% on acceptance. In either case the contract should state that if the mould fails acceptance the deposit is refunded, with a penalty of 1-2 times the deposit in the strictest form. We recommend 30/40/30 for any tool above about USD 5,000 because it ties the largest payment to a document you can read.
Who owns a private mould made in China?
The brand that paid for it. A private mould belongs to the brand; the partner factory holds it in custody and has the right to use it only for that brand's orders. The contract should state ownership, the custody and maintenance duty, that the mould may not be used for any third party, and that the brand may have it transferred to another factory at any time on written notice, usually after any outstanding balance is settled. If a supplier resists writing this down, treat that as your answer.
How many cycles does an injection mould last?
A properly built steel injection mould is generally rated for about 800,000 cycles. With disciplined first-line maintenance by the operators (cleaning, lubrication, daily checks) and second-line maintenance by tool fitters (polishing, weld repair, guide-pin and spring replacement by matching colour, outer diameter and length), the same tool can run 2-3 times that. Factories that skip maintenance typically get one-fifth to one-third of the rated life, which is why the maintenance duty belongs in the mould agreement.
How much does a glass bottle mould cost?
Glass moulds are cheaper than plastic injection moulds because the cavity is simpler. A hand-blown mould is about RMB 2,500 per set (approximately USD 350); an automatic-line mould about RMB 4,000 per set (approximately USD 555); a 4-cavity to 8-cavity set for an automatic line runs RMB 16,000-32,000 (approximately USD 2,200-4,450), depending on the glassworks. Custom glass usually carries a 30,000-200,000 piece minimum and a 30-60 day lead time, so the mould fee is rarely the deciding cost.
What should a private-mould supply contract include?
Six clauses that cost nothing to write and a great deal to omit: capacity reserved at 120% of forecast order volume; a price-adjustment trigger when resin or raw-material prices move more than plus or minus 10%; mould ownership with the brand and use restricted to the brand's orders; an anti-counterfeit provision with a cost-sharing scheme for security codes; MOQ flexibility so that surplus above 20% of the order can be cancelled; and an automatic switch to a qualified second source if the primary factory fails to supply for 5 days or more. We also recommend a re-quote line: if a buyer pushes more than 10% below the estimate, the toolmaker should re-review the specification rather than cut steel quality.
Planning a private mould?

Get the mould quote itemised before you pay a deposit.

Send us the component and the annual volume. Your quote comes with the eight cost lines, the cavity recommendation, the 30/40/30 schedule and the ownership clause already in it.

Reply within 24h · NDA on request · Your details stay confidential

Keep Reading

Related reading.